Extension build timelines in Ireland (14 to 26 weeks)

Most Irish single-storey rear extensions spend 14 to 18 weeks on site from excavation to handover. Wrap-around builds take 16 to 22 weeks, and two-storey extensions run 20 to 26 weeks, excluding pre-build drawings or council planning.

Realistic site schedules from first digger day to snag handover, plus pre-construction drawings, glazing lead times and screed drying.

Free, no obligation. One local builder prices it, not five.

  • 14–18 wkssingle-storey rear on site
  • 16–22 wkswrap-around L-shape on site
  • 20–26 wkstwo-storey build on site
  • 6–10 wkstypical custom glazing lead time
Scaffolding around blockwork walls and a horizontal steel beam during a two-storey semi-detached house extension

Week-by-week construction sequence (35 m² single-storey build)

Knowing the real sequence on site helps you plan glazing orders, kitchen templating, temporary accommodation and stage-payment drawdowns without rushing drying times that cause cracked plaster or lifted timber floors.

Weeks 1–3: Groundworks & slab

Typical weeks
3 weeks
Key site milestones
Site set-up, drain diversion, strip/raft concrete pour, rising walls, radon barrier and floor slab.

Weeks 4–7: Shell, RSJ & roof

Typical weeks
4 weeks
Key site milestones
Blockwork or timber frame walls up to wall plate, roof structure, waterproofing membrane and fascia.

Weeks 8–10: Knock-through & glazing

Typical weeks
3 weeks
Key site milestones
Propping, steel RSJ installation, padstones, fitting triple-glazed patio doors and roof windows.

Weeks 11–13: First fix & wet plaster

Typical weeks
3 weeks
Key site milestones
Electrical cabling, heating/plumbing pipework, insulation, drylining, sand-cement render and skim.

Weeks 14–18: Screed dry, second fix & snag

Typical weeks
4 to 5 weeks
Key site milestones
Floor screed curing, kitchen fitting, tiling, sanitaryware, painting, electrical certs and final snag list.

Price my extension

Four quick taps and our builder m² guide shows before we ask for a phone number. One local builder rings you, not five.

A single-storey rear extension, 25 to 40 m², full turnkey (drawings ready): €83,000 to €118,000, incl. 13.5% VAT.

Step 1 of 5

What kind of extension?

Pick the closest layout. The builder checks tie-ins and structure on site.

How the m² build guide is worked out

The range reflects going Irish extension builder tender rates incl. 13.5% VAT for that layout, floor area and finish stage. Builder's finish covers substructure, strip footings, walls, RSJ steelwork, roof, windows, external render, drylining, screed and first-fix plumbing and electrics. Full turnkey adds kitchen units, sanitaryware, tiling, flooring and decorating allowances. Dublin, Wicklow, Kildare and Meath carry an 8% regional adjustment for site access and labour. Piled foundations on peat, heavy box-frame steel, drain diversions and architect or engineer fees are confirmed separately after reviewing drawings or inspecting the site.

Four scheduling bottlenecks Irish builders warn about

  • Order patio doors as soon as masonry opes are confirmed. Custom thermally broken aluminium sliders and aluclad doors commonly carry 6 to 10 week factory lead times; late orders leave the shell sitting open waiting to dry out.
  • Respect concrete screed and plaster drying windows. Laying engineered oak or glued herringbone flooring over damp screed warps boards within weeks; allow roughly 1 day per mm of sand-cement screed depth (or specify rapid-dry liquid screed).
  • Pre-construction time sits outside the site schedule. Allow 4 to 8 weeks for measured surveys, architect tender packs and builder pricing on exempt jobs, or 16 to 26 weeks when full council planning and BCAR notices apply.
  • Winter weather affects external render and footings. External monocouche or sand-cement render cannot be applied below 5°C or in driving frost; winter starts often finish the inside first and complete final exterior coats in spring.

Common questions before you tender

How long does a 30 m² rear extension take to build in Ireland?

Allow 14 to 18 weeks on site for a full turnkey single-storey build, or 10 to 13 weeks to reach builder's finish (shell and core).

How long does a two-storey extension take?

Two-storey builds typically run 20 to 26 weeks on site due to scaffolding, roof restructuring, extra blockwork curing, upstairs plumbing and larger plastering area.

What delays Irish house extensions most often?

Late changes to kitchen or electrical layouts after first fix, unmapped foul drains discovered on excavation, slow custom glazing deliveries, and starting without complete working drawings.

When should I book an extension builder?

Good local Irish contractors typically book 3 to 6 months ahead. Share your rough outline or planning drawings early so you secure a start slot while tender specs are finalised.

Every extension build page and technical guide

A finished rear extension living room with wide sliding glass doors opening onto a slate patio and green garden

See your m² build range before a builder rings

Pick the extension type, floor area and finish stage. When you want a written tender price, your outline goes to one local extension builder in your county.