Builder's finish (shell & core) vs full turnkey
Builder's finish (shell and core) tenders at €1,850 to €2,550/m² incl. 13.5% VAT, delivering a weathertight, glazed, plastered shell with first-fix services. Full turnkey runs €2,600 to €3,800/m², adding kitchen, sanitaryware, tiling, flooring and painting under one main contract.
Where the main contractor stops on a builder's finish contract, what you save on paper, and when managing second-fix yourself actually pays off.
Free, no obligation. One local builder prices it, not five.
- €1,850–€2,550/m²builder's finish (shell & core)
- €2,600–€3,800/m²full turnkey incl. 13.5% VAT
- €750–€1,250/m²typical fit-out & finish gap
- 1 contractsingle warranty on turnkey

Line-by-line contract boundary compared
Homeowners comparing two builder quotes often miss that one contractor priced to builder's finish while the second priced turnkey. Putting every work package in the right column before signing avoids €20,000+ budget shocks midway through the build.
Builder's finish (shell & core)
- Substructure & drains
- Included: footings, radon slab, drain diversions
- Structure, RSJ & roof
- Included: walls, steel beams, roof, fascia & render
- Windows & external doors
- Included: fitted, airtight-taped & sealed
- Plumbing & electrics
- First fix (pipes & cables in walls) + basic white sockets/boiler tie-in
- Walls & floor prep
- Drylined, skim-plastered walls & levelled concrete screed
- Kitchen, tiles & sanitaryware
- Excluded (sourced & fitted by homeowner after handover)
Full turnkey delivery
- Substructure & drains
- Included
- Structure, RSJ & roof
- Included
- Windows & external doors
- Included
- Plumbing & electrics
- Full first + second fix, feature lighting, heated rails & commissioning certs
- Walls & floor prep
- Plastered, primed, painted + timber/tile floors laid
- Kitchen, tiles & sanitaryware
- Included via agreed PC sums and builder-managed fitting
Price my extension
Four quick taps and our builder m² guide shows before we ask for a phone number. One local builder rings you, not five.
A single-storey rear extension, 25 to 40 m², builder's finish (drawings ready): €59,000 to €82,000, incl. 13.5% VAT.
How the m² build guide is worked out
The range reflects going Irish extension builder tender rates incl. 13.5% VAT for that layout, floor area and finish stage. Builder's finish covers substructure, strip footings, walls, RSJ steelwork, roof, windows, external render, drylining, screed and first-fix plumbing and electrics. Full turnkey adds kitchen units, sanitaryware, tiling, flooring and decorating allowances. Dublin, Wicklow, Kildare and Meath carry an 8% regional adjustment for site access and labour. Piled foundations on peat, heavy box-frame steel, drain diversions and architect or engineer fees are confirmed separately after reviewing drawings or inspecting the site.
When builder's finish saves real money, and when turnkey wins
- When builder's finish works well: You already have trusted direct kitchen makers, tilers and decorators, have spare time to schedule deliveries, and want to keep 10% to 15% main-contractor coordination markup out of bespoke kitchen or stone purchases.
- When turnkey works better: You are working full time or living in the house with children and want one builder coordinating plumber, electrician, tiler and kitchen fitter so nobody blames another crew for delays or cracked tiles.
- Watch Prime Cost (PC) sums inside turnkey tenders. A cheap turnkey quote sometimes hides an unrealistic €6,000 kitchen PC sum or €20/m² tile allowance; insist PC sums match real Irish showroom figures before signing.
- Check VAT on direct supply vs builder supply. A kitchen supplied and fitted by your builder or kitchen firm under a supply-and-install contract qualifies for 13.5% VAT (two-thirds rule); loose appliances bought online carry 23% VAT.
Related builder & stage guides
Build rates per m²Stage-by-stage Irish builder rates incl. 13.5% VAT and county weighting.
Tendering a builderTender packs, bill of quantities, RIAI stage payments and 13.5% VAT.
Single-storey rear builders25 to 40 m² rear kitchen builds, RSJ knock-throughs and m² rates.
Steel RSJs & sign-offBox frames, padstones, temporary propping and structural certs.
Build timelinesWeek-by-week 14 to 26 week construction stages and drying times.
Part L thermal & B2 BERWall/roof U-values and the >25% surface area Major Renovation rule.Common questions before you tender
How much cheaper is builder's finish on a 35 m² extension?
At €1,850 to €2,550/m² versus €2,600 to €3,800/m², the main builder's contract sits €26,000 to €44,000 lower at handover. You then spend €20,000 to €38,000 directly on kitchen, flooring, tiling, sanitaryware and painting.
Does builder's finish include windows and patio doors?
Yes. Standard Irish builder's finish always leaves the extension completely weathertight with external windows, sliding or bifold doors, roof glazing, external render and internal plaster skim completed.
Are internal doors and skirting included in builder's finish?
Usually no, or only basic primed MDF skirting and standard flush doors if specifically written in. Always confirm second-fix carpentry (internal doors, architrave, skirting, window boards) explicitly in the quote.
Will an electrician certify first-fix only on a builder's finish?
Safe Electric Completion Certificates are issued only once second-fix sockets, switches, circuit breakers and earth testing are complete. Keep the same Registered Electrical Contractor through to final commissioning.
Every extension build page and technical guide
Extension build types
Construction stages & rules

See your m² build range before a builder rings
Pick the extension type, floor area and finish stage. When you want a written tender price, your outline goes to one local extension builder in your county.