Class 1 planning exemptions for Irish house extensions
Under Class 1 of the Planning and Development Regulations 2001 (S.I. No. 600 of 2001), a rear extension is normally exempt up to 40 m² aggregate floor area (including any previous extensions) provided at least 25 m² of private rear open space remains. First-floor rear exemptions cap at 12 m² for terraced or semi-detached homes (with a 2 m party boundary setback) and 20 m² for detached houses, with upper windows kept 11 m from any facing boundary.
The exact statutory limits under S.I. No. 600 of 2001: 40 m² aggregate floor area, 25 m² remaining garden, first-floor caps, window setbacks and €80 Section 5 checks.
Free, no obligation. One local builder prices it, not five.
- 40 m²aggregate rear floor area cap
- 25 m²private rear open space kept
- 12 / 20 m²upper floor semi vs detached cap
- 2 m / 11 mparty wall & upper window setbacks

Every Class 1 statutory condition under S.I. No. 600 of 2001
Domestic rear extensions are governed by Schedule 2, Part 1, Class 1 of the Planning and Development Regulations 2001 (S.I. No. 600 of 2001). Every single condition below must be met together; breaching even one moves the project into a full planning application.
- Aggregate 40 m² floor area cap. Any earlier rear extension built since 1 October 1964 (or since the original house grant) counts toward the 40 m² allowance. If a house already has an old 14 m² rear kitchen, only 26 m² remains exempt unless the old extension is demolished.
- Minimum 25 m² private open space remaining. The council measures clear usable rear garden left over after construction. Sheds or paved parking spaces do not create extra exemption room if total open rear garden drops below 25 m².
- First-floor limits (12 m² semi/terrace, 20 m² detached). On a terraced or semi-detached dwelling, any upper-storey rear extension cannot exceed 12 m² and must stay at least 2 m clear of any party boundary.
- Window proximity (1 m ground, 11 m upstairs). A ground-floor window cannot sit within 1 m of the boundary it faces. Any window above ground level must sit at least 11 m from the boundary it faces.
- Roof height and eaves caps. A flat-roofed extension cannot rise above the eaves of the existing house. A pitched roof cannot exceed the highest ridge of the existing house, and the roof cannot be used as a balcony or terrace.
Price my extension
Four quick taps and our builder m² guide shows before we ask for a phone number. One local builder rings you, not five.
A single-storey rear extension, 25 to 40 m², full turnkey (early planning): €83,000 to €118,000, incl. 13.5% VAT.
How the m² build guide is worked out
The range reflects going Irish extension builder tender rates incl. 13.5% VAT for that layout, floor area and finish stage. Builder's finish covers substructure, strip footings, walls, RSJ steelwork, roof, windows, external render, drylining, screed and first-fix plumbing and electrics. Full turnkey adds kitchen units, sanitaryware, tiling, flooring and decorating allowances. Dublin, Wicklow, Kildare and Meath carry an 8% regional adjustment for site access and labour. Piled foundations on peat, heavy box-frame steel, drain diversions and architect or engineer fees are confirmed separately after reviewing drawings or inspecting the site.
Common Irish extension layouts checked against Class 1
Single-storey rear build up to 40 m²
- Statutory position
- Normally Class 1 exempt
- Hard statutory check
- Aggregate total incl. prior extensions <= 40 m²; >= 25 m² rear garden kept
Two-storey rear on terraced or semi-detached
- Statutory position
- Exempt only to 12 m² upstairs
- Hard statutory check
- Upper floor <= 12 m², >= 2 m from party boundary, combined <= 40 m²
Two-storey rear on detached house
- Statutory position
- Exempt only to 20 m² upstairs
- Hard statutory check
- Upper floor <= 20 m², combined ground + first <= 40 m², windows >= 11 m back
Side extension or wrap-around visible from road
- Statutory position
- Planning permission required
- Hard statutory check
- Class 1 applies strictly behind the rear wall of the original house
Front porch extension
- Statutory position
- Class 7 exempt up to 2 m²
- Hard statutory check
- Max 2 m² floor area, 3 m flat / 4 m pitched height, >= 2 m off public road
Protected structure or ACA
- Statutory position
- Exemptions do not apply
- Hard statutory check
- Apply to the local authority before any external masonry or window alteration
Section 5 declarations and BCAR over 40 m²
Locking in certainty with Section 5 (€80)
If your solicitor will later need proof of compliance when selling or remortgaging, apply to your local authority for a Section 5 Declaration of Exempted Development under the Planning and Development Act 2000. The statutory fee is €80 and the council must decide within 4 weeks.
Why 40 m² also matters for Building Control (BCAR)
Under the Building Control (Amendment) Regulations (S.I. No. 9 of 2014), extensions of 40 m² or less do not require a formal BCMS Commencement Notice. Once floor area crosses 40 m², you must lodge a Commencement Notice 14 to 28 days before starting on site and appoint either an Assigned Certifier or lodge a homeowner Opt-Out Declaration. Either way, every exempt extension must still satisfy all Technical Guidance Documents including Part L thermal rules and structural Part A.
Common questions before you tender
Does an old lean-to or conservatory count inside my 40 m² Class 1 allowance?
Yes. The 40 m² limit is aggregate floor area across all rear extensions added to the original house. Demolishing a 12 m² old sunroom resets that 12 m² back into your allowance.
Can I build a side extension without planning permission?
No. Class 1 covers extensions strictly to the rear of the house. Building to the side or wrapping along the side wall visible from the street requires planning permission.
Do I need a Commencement Notice for a 35 m² rear extension?
No. Under BCAR, extensions up to 40 m² are exempt from lodging a Commencement Notice, though builders must still build strictly to Irish Building Regulations and structural engineer certificates are strongly advised for resale.
What is the planning limit for a front porch in Ireland?
Under Class 7, a front porch up to 2 m² internal floor area is normally exempt provided it stays at least 2 m from a public road and stays under 3 m high (flat roof) or 4 m (pitched).
How long does full planning permission take if I build over 40 m²?
Allow 8 weeks for the council decision period from validation plus 4 weeks for the An Bord Pleanála appeal window (12 weeks minimum, or 16 to 24 weeks if Further Information is requested).
Every extension build page and technical guide
Extension build types
Construction stages & rules

See your m² build range before a builder rings
Pick the extension type, floor area and finish stage. When you want a written tender price, your outline goes to one local extension builder in your county.